MAZAR-E-SHARIF, AFGHANISTAN

FLOOD PROTECTION

MEASURES

 03   /   2014

 06   /   2014

The Project consisted of Construction of

1500m Flood Dam in Mazar-e-Sharif Airport

to Prevent Flood Penetration. The project 

began in March 2014, and was completed in

June 2014.

90

DAYS

$500K

1200px-KfW_Bankengruppe.svg.png

PROJECT TIMELINE

TOTAL BUDGET

CLIENT